The last segment of the superstructure, 16.11.2010

     The assembly of the last segment of the superstructure of Danube Bridge Vidin-Calafat in the non-navigable channel of the river was completed – from the first to the eight pier. The total number of the assembled concrete segments is 292. Each of them was produced according to individual parameters in the production plant of FCC Construccion, situated in the vicinity of the construction. The length of the superstructure in this part of the river is 650 meters.

   In the navigable channel of the Danube the superstructure will be made with bigger segments, which are being produced and stored  in the production plant.

     Cantilever wings are being constructed on both sides of the deck of the superstructure with the help of self-moving cantilever installation.

 